Project Details

REGION III - CENTRAL LUZON : PROVISION OF POTABLE WATER SUPPLY (LEVEL 3)
BALER (Capital), AURORA


PROJECT IMAGES

I. PROJECT PROFILE

RegionREGION III - CENTRAL LUZON
ProvinceAURORA
City/MunicipalityBALER (Capital)
Barangay/s
  • Barangay I (Pob.)
  • Barangay II (Pob.)
  • Barangay III (Pob.)
  • Barangay IV (Pob.)
  • Barangay V (Pob.)
  • Pingit
  • Sabang
  • Suclayin
  • Zabali
Name of ProgramADM - WATER
Project CodeADM-PW-17-03-70-01-000-1
Project TitlePROVISION OF POTABLE WATER SUPPLY (LEVEL 3)
Description of ProjectCONSTRUCTION, REPLACEMENT/UPGRADING/REHABILITATION OF DEEPWELL, ELEVATED STORAGE TANK, TREATMENT FACILITY, EXPANSION OF TRANSMISSIONS, DISTRIBUTION LINES, SERVICE CONNECTIONS WITH WATER METERS
Funding Year2017
National Subsidy (Original Allocation)14,189,000.00
Type of ProjectWATER SYSTEM
Sub Type of ProjectWATER SYSTEM
Project Type (as per Procurement Process)Infrastructure
Exact LocationBRGYS. 01, 02, 03, 04, 05 POBLACION, BRGYS. SUKLAYIN, PINGIT, ZABALI & SABANG, BALER, AURORA
Beneficiaries6736
StatusCOMPLETED
Remarks

II. IMPLEMENTATION INFORMATION

National Subsidy (Cancelled Allocation)Php 0.00
National Subsidy (Revised Allocation)Php 14,189,000.00
National Subsidy (Reverted Amount)Php 0.00
LGU Counterpart/Cash Equity (Original Allocation)Php 0.00
LGU Counterpart/Cash Equity (Cancelled Allocation)Php 0.00
LGU Counterpart (Reverted Amount)Php 0.00
LGU Counterpart/Cash Equity (Revised Allocation)Php 0.00
Total Project CostPhp 14,189,000.00
Implementing UnitMunicipal LGU
Mode of ImplementationContract

  A. CONTRACT DETAILS

Name of ContractorGeoravin Construction & Supplies
Office AddressPoblacion West, Labrador, Pangasinan
Date of Perfection of Contract2017-11-15
Date of Receipt of Notice to Proceed2017-11-16
Contract AmountPhp 14,184,833.89
Contract Duration240
Intended Completion Date2018-07-13