REGION VIII - EASTERN VISAYAS : "PROVISION OF RAIN WATER CATCHMENT FACILITY IN 1. NEW MUN. BLDG., BRGY. BAWOD 2. BFP, BRGY. CROSSING 3. WOMEN CENTER, BRGY. CROSSING 4. BUGNAY EVAC CENTER, BRGY. BASUD 5. MUERTIGUE EVAC CENTER, BRGY. DAJA DIOT 6. WET MARKET BLDG., BRGY. BAWOD 7. CR MARKET BLDG., BRGY. BAWOD 8. SINHS 9. MNHS, BRGY. DAJA DIOT 10. SI CENTRAL SCHOOL"
SAN ISIDRO, LEYTE


PROJECT IMAGES

No images uploaded.

I. PROJECT PROFILE

RegionREGION VIII - EASTERN VISAYAS
ProvinceLEYTE
City/MunicipalitySAN ISIDRO
Barangay/s
  • Basud
  • Bawod (Pob.)
  • Crossing (Pob.)
  • Daja-diot
Name of ProgramAM-PW
Project CodeAM-PW-19-08-37-42-000-3
Project Title"PROVISION OF RAIN WATER CATCHMENT FACILITY IN 1. NEW MUN. BLDG., BRGY. BAWOD 2. BFP, BRGY. CROSSING 3. WOMEN CENTER, BRGY. CROSSING 4. BUGNAY EVAC CENTER, BRGY. BASUD 5. MUERTIGUE EVAC CENTER, BRGY. DAJA DIOT 6. WET MARKET BLDG., BRGY. BAWOD 7. CR MARKET BLDG., BRGY. BAWOD 8. SINHS 9. MNHS, BRGY. DAJA DIOT 10. SI CENTRAL SCHOOL"
Description of Project-
Funding Year2019
National Subsidy (Original Allocation)943,000.00
Type of ProjectWATER SYSTEM
Sub Type of ProjectRAIN WATER CATCHMENT FACILITIES
Project Type (as per Procurement Process)Infrastructure
Exact Location1. NEW MUN. BLDG@BAWOD,BFP@CROSSING,WOMEN CENTER@CROSSING,BUGNAY EVAC CENTER@BASUD,MUERTIGUE EVAC@DAJA DIOT,WET MARKET BLDG@BAWOD,CR MARKET BLDG@BAWOD,SINHS,MNHS@DAJA DIOT, &SI CENTRAL
Beneficiaries650
StatusNOT YET STARTED
Remarks

II. IMPLEMENTATION INFORMATION

National Subsidy (Cancelled Allocation)Php 0.00
National Subsidy (Revised Allocation)Php 943,000.00
National Subsidy (Reverted Amount)Php 0.00
LGU Counterpart/Cash Equity (Original Allocation)Php 0.00
LGU Counterpart/Cash Equity (Cancelled Allocation)Php 0.00
LGU Counterpart (Reverted Amount)Php 0.00
LGU Counterpart/Cash Equity (Revised Allocation)Php 0.00
Total Project CostPhp 943,000.00
Implementing UnitMunicipal LGU
Mode of ImplementationContract

  A. CONTRACT DETAILS

Name of ContractorRed Axe Builders and Supply
Office AddressCapt. D. Vilbar St., Hilongos, Leyte
Date of Perfection of Contract2020-01-23
Date of Receipt of Notice to Proceed2020-01-27
Contract AmountPhp 942,500.00
Contract Duration60
Intended Completion Date2020-04-03